Historical crane on the redesigned original trestle bridge as a memorial of Gdansk Shipyard
Main Article Content
DOI
Authors
Abstract
The paper includes selected aspects of the study, whose goal is to hold the historical crane 642-24 in its current location after the modification of trestle bridge static scheme. The scope of the paper includes the assessment of current technical condition of the object, a presentation of FEM analyses, a description of the assumed load cases, results of the static calculations, checking the effort of construction elements, global and local structure stability and its dynamic characteristics.
Keywords:
crane, Gdansk Shipyard, FEM analysis, expert opinion
Downloads
Article Details
Chróścielewski, J., Miśkiewicz, M. and Pyrzowski, Łukasz (2013) “Historical crane on the redesigned original trestle bridge as a memorial of Gdansk Shipyard”, Budownictwo i Architektura, 12(3), pp. 247–254. doi: 10.35784/bud-arch.2039.